Standards
Designed to the specification, line by line
Compliance matrix
The design meets the requirement as written.
Designed to meet it; a test or datasheet review will confirm before deployment.
Depends on a supplier's documented rating or approval.
Agreed with the agency for each project, for example in the system plan.
Every requirement in the matrix
Traffic control devices
Signs and their placement follow the national manual; the contractor's traffic control plan governs the layout.
Portable changeable message signs: visible from ½ mile, 18-inch characters, at most two phases
Designed toMUTCD 11th Edition §6L.05
Full-matrix signs; the message library and rules enforce the line, character and phase limits.
Sign spacing, taper and buffer lengths
Designed toMUTCD Tables 6B-1 to 6B-4
Devices are placed around the approved traffic control layout, never in place of it.
Messages coordinated with the agency's public information staff
Set per projectAgency contract provisions
Pre-approved message library, an approval workflow for anything else, and an audit log.
Speed limit changes inside an approved envelope
Set per projectAgency speed limit authorization
Pace schedules and remote changes are limited to the approved speeds and logged.
Crashworthiness of devices in the clear zone
Vendor confirmationFHWA crashworthiness policy; MASH
Trailers sited outside the clear zone or shielded or delineated; cone-mounted sensors need the supplier's evidence.
Smart work zone devices
Current state DOT smart work zone specifications set minimums for each device type. The design targets them directly.
Camera: pan-tilt-zoom on a mast of at least 20 ft with at least 20× zoom
Designed toState DOT smart work zone device specifications
Lookout: 40× PTZ on a mast of up to 30 ft.
Traffic detection with per-lane speed, volume and occupancy
Verification plannedState DOT smart work zone device specifications
Side-fire radar to 255 ft on up to 16 lanes; the ¼-mile detection clause is under datasheet review.
Variable speed limit sign with speed feedback
Designed toState DOT smart work zone device specifications
Pace: R2-1 48 × 60 in, 5-mph steps, feedback to 95 mph.
Power: visible charge status, 4 h of sun, 10 days of autonomy, automatic restart
Verification plannedState DOT smart work zone device specifications
Power budgets per node with separate add-on batteries; cold-chamber test before the fleet purchase.
Trailers: unit number, 80-mph wind rating with anchoring, outriggers, lights, highway orange
Vendor confirmationState DOT smart work zone device specifications
Written into every trailer order, with the wind rating required at full mast height.
Data and connectivity
The data requirements are where smart work zones most often fall short. They are designed in from the start.
WZDx device feed, updated every 60 seconds, with version tracking
Designed toUSDOT Work Zone Data Exchange (WZDx) 4.2
Command publishes the device feed every 60 seconds and tracks new WZDx releases.
GPS position within 10 ft and time-stamped device status
Designed toState DOT smart work zone device specifications
GNSS on every node (about 2 m); status with time stamps in every report.
60-second data bins; bad data corrected within 1 hour
Designed toState DOT smart work zone system specifications
Edge binning on every node; data-quality alerts to the on-call team.
Archive of all data, messages and status for at least 3 years
Designed toState DOT smart work zone system specifications
Command archive with CSV and Excel export, kept 3 years after the project or handed to the agency.
Software availability of at least 99%
Designed toState DOT smart work zone system specifications
Command is designed for 99.9% monthly availability.
Security, accessibility and procurement
Federal-aid projects bring rules about equipment origin, radio licensing and data handling.
No covered telecommunications or video surveillance equipment
Designed toNDAA §889; 2 CFR 200.216
No equipment from the covered manufacturers in any LaneWarden node; component origin checked for supplied items.
Role-based access, MFA, session timeouts, audit logging, vulnerability scanning
Verification plannedAgency cyber and information security policies
Least-privilege roles, SSO with MFA for privileged users, 20-minute timeouts, audit logs; security audit planned.
Accessible web interface
Verification plannedWCAG 2.1 AA
Command's web interface is built to WCAG 2.1 AA; full conformance needs testing with assistive technology.
Media sanitization at demobilization
Designed toNIST SP 800-88
Every storage device is sanitized and the sanitization recorded when equipment leaves the project.
Radio equipment authorization
Vendor confirmationFCC Parts 15 and 90
Authorized equipment only; licensed paging only where a project uses it.
Guides
Go deeper
Fundamentals
What is a smart work zone?
Sensors, message signs, software and a team that runs them, set up for the life of a construction project. What a smart work zone is, what it does and how agencies ask for one.
4 min read
Data
WZDx device feeds, explained
The Work Zone Data Exchange gives agencies and navigation services one format for work zones and the devices in them. What the device feed contains, field by field, with an example.
3 min read
Next step
Working through a smart work zone specification?
Send us the special provisions. We will show how each clause would be met, and which ones need a decision from the agency.